[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939120":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939120,606,1,"单选题","已知某工程的进度计划安排如下图，其中工作 J 的最早开始时间为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":18},"B","5",true,{"key":20,"text":21,"correct":14},"C","7",{"key":23,"text":24,"correct":14},"D","8","本题考查的是制定进度计划的方法。由图中可以看出工作 J 的紧前工作是 E 和 F，所有工作 J 的最早开始时间=max{（2+2），（2+3），（2+3）}=5（天）",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]