[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939119":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939119,606,1,"单选题","在工程网络计划中，关键工作是指（ ）的工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最迟完成时间与最早完成时间的差值最小",true,{"key":16,"text":17,"correct":18},"B","双代号时标网络计划中无波形线",false,{"key":20,"text":21,"correct":18},"C","单代号搭接网络计划中时间间隔为零",{"key":23,"text":24,"correct":18},"D","双代号网路计划中两端节点均为关键节点","本题考查的是制定进度计划的方法。关键工作指的是网络计划中总时差最小的工作。而总时差等于其最迟开始时间减去最早开始时间，或等于最迟完成时间减去最早完成时间。故选项 A 正确；选项 B，波形线代表的是本工作的自由时差，无波形线只能说明该项工作的自由时差等于零，该项工作不一定是关键工作；选项 C，单代号搭接网络计划中与紧后工作之间时间间隔为零，只能说明紧后工作的最早开始时间等于该项工作的最早完成时间，该项工作不一定就是关键工作；选项 D，双代号网路计划中两端节点均为关键节点的工作不一定就是关键工作。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]