[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939117":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939117,606,1,"单选题","某双代号网络图如下图所示，下列选项描述正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","虚工作 2-3 是多余的",false,{"key":16,"text":17,"correct":14},"B","虚工作 4-5 是多余的",{"key":19,"text":20,"correct":14},"C","虚工作 5-6 是多余的",{"key":22,"text":23,"correct":24},"D","所有虚工作均为必要的",true,"本题考查的是工作顺序安排。为了避免两项同时开始、同时进行的工作具有相同的开始节点和完成节点，也需要用虚工作加以区分。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]