[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939116":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939116,606,1,"单选题","某双代号网络图有 A、 B、 C、 D、E 五项工作，其中 A、B 完成后 D 开始， B、C 完成后 E 开始，能够正确表达上述逻辑关系的图形是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","图 1",false,{"key":16,"text":17,"correct":14},"B","图 2",{"key":19,"text":20,"correct":14},"C","图 3",{"key":22,"text":23,"correct":24},"D","图 4",true,"本题考查的是工作顺序安排。选项A，图1中③④之间没有工作，虚线表示。选项BC，图2和图3中没有表达AB完成后开始D的逻辑关系。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]