[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939115":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939115,606,1,"单选题","如果网络计划中某项工作进度拖延的时间超过其（ ），则无论该工作是否为关键工作，其实际进度都将对后续工作的总工期产生影响",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总时差",true,{"key":16,"text":17,"correct":18},"B","自有时差",false,{"key":20,"text":21,"correct":18},"C","最早结束时间",{"key":23,"text":24,"correct":18},"D","最迟结束时间","本题考查的是制定进度计划的方法。如果网络计划中某项工作进度拖延的时间超过其总时差，则无论该工作是否为关键工作，其实际进度都将对后续工作的总工期产生影响。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]