[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939114":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939114,606,1,"单选题","工期优化一般通过压缩（ ）的持续时间来进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","有充足备用资源的非关键工作",false,{"key":16,"text":17,"correct":14},"B","缩短持续时间对安全影响大的关键工作",{"key":19,"text":20,"correct":21},"C","缩短持续时间增加费用最少的关键工作",true,{"key":23,"text":24,"correct":14},"D","缩短持续时间对质量影响不大的非关键工作","本题考查的是进度计划优化。工期优化是指压缩计算工期以满足工期要求，或在一定条件下使工期最短的过程。工期优化一般通过压缩关键工作的持续时间来进行。选择应缩短持续时间的关键工作应考虑下列因素：（1）缩短持续时间对质量和安全影响不大的工作；（2）有充足备用资源的工作；（3）缩短持续时间增加费用最少的工作。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]