[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939113":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939113,606,1,"单选题","项目日历中规定了可以开展进度活动的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作日和工作班次",true,{"key":16,"text":17,"correct":18},"B","工作地点和工作班次",false,{"key":20,"text":21,"correct":18},"C","工作日和工作强度",{"key":23,"text":24,"correct":18},"D","工作地点和工作强度","本题考查的是进度计划编制的成果。项目日历中规定了可以开展进度活动的工作日和工作班次。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]