[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939112":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939112,606,1,"单选题","工程项目进度管理工作包括：①工作定义；②工作顺序安排；③工作进度控制；④工作进度计划制定；⑤工作时间估算。正确的顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①—②—③—④—⑤",false,{"key":16,"text":17,"correct":18},"B","①—②—⑤—④—③",true,{"key":20,"text":21,"correct":14},"C","①—③—②—⑤—④",{"key":23,"text":24,"correct":14},"D","①—⑤—②—③—④","本题考查的是工程项目进度管理概述。工程项目进度管理流程为：规划进度管理→工作定义→工作顺序安排→工作资源估算→工作时间估算→进度计划制定→进度控制。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]