[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939108":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939108,606,1,"单选题","先将所有节点按其最早时间定位在时标网络计划表中的相应位置，然后再用规定线型（实箭线和虚箭线）按比例绘出工作和虚工作是（ ）的绘制步骤。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接绘制法",false,{"key":16,"text":17,"correct":18},"B","间接绘制法",true,{"key":20,"text":21,"correct":14},"C","规定型绘图法",{"key":23,"text":24,"correct":14},"D","非规定型绘图法","本题考查的是工作顺序安排。间接绘制法，其绘制步骤是先将所有节点按其最早时间定位在时标网络计划表中的相应位置，然后再用规定线型（实箭线和虚箭线）按比例绘出工作和虚工作。直接绘制法，是指不计算时间参数而直接按无时标的网络计划草图绘制时标网络计划。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]