[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939107":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939107,606,1,"单选题","某项目采用三时估算法估算工作时间，乐观时间、最可能时间和最保守时间，分别是 10 天、16 天、21 天，则此活动的期望时间是（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":18},"B","16",true,{"key":20,"text":21,"correct":14},"C","17",{"key":23,"text":24,"correct":14},"D","18","本题考查的是工作时间估算。专家判断估算常采用三时估算法，即工作所需时间期望值=（a+4m+b）\u002F6=（10+4×16+21）\u002F6=15.83（天）≈16（天）。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]