[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939105":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939105,606,1,"单选题","下列不属于工作定义成果的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作清单",false,{"key":16,"text":17,"correct":14},"B","里程碑清单",{"key":19,"text":20,"correct":14},"C","工作分解结构",{"key":22,"text":23,"correct":24},"D","进度计划制定",true,"本题考查的是工程项目工作定义。工作定义的成果包括：工作清单；工作属性；里程碑清单；修正的工作分解结构",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]