[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939104":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939104,606,1,"单选题","下列不属于工程项目进度控制结果的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制进度计划",true,{"key":16,"text":17,"correct":18},"B","工作绩效信息",false,{"key":20,"text":21,"correct":18},"C","项目文件更新",{"key":23,"text":24,"correct":18},"D","项目管理计划更新","本题考查的是项目进度控制的工作成果。工程项目进度控制的结果包括：工作绩效信息；进度预测；变更请求；项目管理计划更新；项目文件更新；组织过程资产更新。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]