[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939102":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939102,606,2,"多选题","进度比较方法中，趋势分析的比较方法包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","横道图法",true,{"key":16,"text":17,"correct":18},"B","时标网络图法",false,{"key":20,"text":21,"correct":14},"C","前锋线",{"key":23,"text":24,"correct":14},"D","列表法",{"key":26,"text":27,"correct":18},"E","里程碑法","ACD","本题考查的是项目进度控制方法。常用的进度比较方法有：趋势分析、关键路径法和挣值管理。趋势分析包括：横道图比较法、前锋线比较法、S形曲线比较法、香蕉曲线比较法、列表比较法。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]