[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939101":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939101,606,2,"多选题","下列关于横道图的表述，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","横道图的优点是简单明了，易于掌握",true,{"key":16,"text":17,"correct":18},"B","横道图的右边按工作的先后顺序列出项目的工作名称",false,{"key":20,"text":21,"correct":14},"C","横道图的缺点是不能全面反映各项工作之间的逻辑关系和整个工程的主次工作",{"key":23,"text":24,"correct":18},"D","横道图的左边是进度表",{"key":26,"text":27,"correct":14},"E","横道图水平线段的位置和长短反映该项目从开始到完工的时间","ACE","本题考查的是项目进度控制方法。横道图的缺点是不能全面反映各项工作之间的逻辑关系和整个工程的主次工作。横道图是传统的进度计划表示方法，其左边按工作的先后顺序列出项目的工作名称，图右边是进度表，图上边的横栏表示时间。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]