[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939095":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939095,606,1,"单选题","某工程双代号时标网络计划如下图所示，其中工作 A 的总时差和自由时差（ ）周",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1；0",true,{"key":16,"text":17,"correct":18},"B","均为 0",false,{"key":20,"text":21,"correct":18},"C","0；1",{"key":23,"text":24,"correct":18},"D","均为 1","本题考查的是工作顺序安排。工作 A 的总时差 1 周、自由时差为 0。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]