[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939094":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939094,606,1,"单选题","关于双代号网络图绘图规则的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","箭线不能交叉",false,{"key":16,"text":17,"correct":14},"B","关键工作必须安排在图面中心",{"key":19,"text":20,"correct":21},"C","只有一个起点节点",true,{"key":23,"text":24,"correct":14},"D","工作箭线只能用水平线","本题考查的是工作顺序安排。箭线交叉可以用指向法或过桥法。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]