[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939093":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939093,606,1,"单选题","规定了用于项目进度规划的方法和工具，对工作排序具有指导作用的工作顺序安排的依据是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作清单",false,{"key":16,"text":17,"correct":14},"B","项目范围说明书",{"key":19,"text":20,"correct":14},"C","环境因素",{"key":22,"text":23,"correct":24},"D","进度管理计划",true,"本题考查的是工作顺序安排。进度管理计划规定了用于项目进度规划的方法和工具，对工作排序具有指导作用。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]