[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939090":3},{"question":4,"library":22},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":21},939090,606,1,"单选题","用双代号绘图法绘制网络图时，某项工作不消耗时间不消耗资源，则该工作用（ ）表示。",[11,14,16,19],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",true,{"key":20,"text":20,"correct":13},"D","本题考查的是工作顺序安排。双代号网络图中的工作通常分为两种：第一种为需要消耗时间和资源，用实箭线表示；第二种为既不消耗时间，也不消耗资源，我们称为虚工作用虚箭线表示。",{"id":6,"name":23,"category":24,"favorite":25},"工程项目组织与管理","建筑工程",0]