[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939089":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939089,606,1,"单选题","工程双代号时标网络计划如图所示，当计划执行到第 5 周末检查时，其实际进度如图中 前锋线所示，检查结果表明( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","D 工作滞后 1 周，不影响总工期",false,{"key":16,"text":17,"correct":14},"B","I 工作滞后 1 周，预计总工期延长 1 周",{"key":19,"text":20,"correct":14},"C","E 工作提前 1 周，预计总工期缩短 1 周",{"key":22,"text":23,"correct":24},"D","H 工作提前 1 周，不影响总工期",true,"H 工作在非关键线路上，提前 1 周，不影响总工期",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]