[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939088":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939088,606,2,"多选题","某工作的实际进度发生偏差，判断其对后续工作和总工期是否产生影响的依据有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程资源的分布是否均衡",false,{"key":16,"text":17,"correct":14},"B","该工程的实际投资是否到位",{"key":19,"text":20,"correct":21},"C","该工作是否处于关键线路",true,{"key":23,"text":24,"correct":21},"D","进度偏差是否超过该工作的总时差",{"key":26,"text":27,"correct":21},"E","进度偏差是否超过该工作的自由时差","CDE","当某项工作发生实际进度偏差时，根据该项工作是否处于关键线路、其进度偏差是 否超过该项工作的总时差和自由时差来判断对后续工作和总工期的影响。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]