[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939087":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939087,606,1,"单选题","进度监测的系统过程，首先进行的工作是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度计划的实施",true,{"key":16,"text":17,"correct":18},"B","建立进度数据采集系统",false,{"key":20,"text":21,"correct":18},"C","数据的整理统计和分析",{"key":23,"text":24,"correct":18},"D","实际进度与计划进度比较","进度监测的系统过程如图 6-41 所示",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]