[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939084":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":23},939084,606,1,"单选题","某工程项目实施过程的部分时间参数如下表所示： 其中，自由时差最大的工作是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","B",false,{"key":13,"text":16,"correct":17},"D",true,{"key":19,"text":20,"correct":14},"C","E",{"key":16,"text":22,"correct":14},"G","自由时差=min(紧后工作的最早开始时间-本工作的最早结束时间) 时标网络计划中：工作自由时差＝波形线在坐标轴上水平投影长度",{"id":6,"name":25,"category":26,"favorite":27},"工程项目组织与管理","建筑工程",0]