[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939083":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939083,606,1,"单选题","某工程项目包括 ABCD 四项工作，工作之间的逻辑关系如下图所示，该项目的工期为( ) 天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","8",{"key":19,"text":20,"correct":14},"C","9",{"key":22,"text":23,"correct":24},"D","10",true,"",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]