[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939082":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939082,606,2,"多选题","下列关于关键线路法的表述，正确的是( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","线路上所有工作持续时间之和为该线路的总持续时间",true,{"key":16,"text":17,"correct":14},"B","总持续时间最长的线路称为关键线路",{"key":19,"text":20,"correct":14},"C","网络计划中关键线路可能不止一条",{"key":22,"text":23,"correct":24},"D","网络计划执行过程中关键线路总是固定不变的",false,{"key":26,"text":27,"correct":24},"E","关键工作的实际进度提前或拖后，不会对总工期产生影响","ABC","D.网络计划执行过程中关键线路可能发生改变。 E.关键工作的实际进度提前或拖后， 会对总工期产生影响",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]