[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939079":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939079,606,1,"单选题","在双代号网络计划中，某一工作的自由时差为其( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","紧后工作的最早开始时间最小值减去本工作的最早完成时间",true,{"key":16,"text":17,"correct":18},"B","紧后工作的最迟开始时间最小值减去本工作的最迟完成时间",false,{"key":20,"text":21,"correct":18},"C","紧后工作的最早开始时间最大值减去本工作的最早完成时间",{"key":23,"text":24,"correct":18},"D","紧后工作的最迟开始时间最大值减去本工作的最迟完成时间","某一工作的自由时差为其紧后工作的最早开始时间最小值减去本工作的最早完成时 间",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]