[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939078":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939078,606,1,"单选题","在双代号网络计划中，工作的最迟完成时间为其所有紧后工作( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","最早开始时间的最大值",false,{"key":16,"text":17,"correct":14},"B","最早开始时间的最小值",{"key":19,"text":20,"correct":14},"C","最迟开始时间的最大值",{"key":22,"text":23,"correct":24},"D","最迟开始时间的最小值",true,"工作最迟完成时间等于其紧后工作最迟开始时间的最小值。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]