[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939077":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939077,606,1,"单选题","工作和工作之间的逻辑关系和工作的持续时间都具有不肯定性而按概率处理的网络计划 技术是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","图示评审技术",true,{"key":16,"text":17,"correct":18},"B","计划评审技术",false,{"key":20,"text":21,"correct":18},"C","关键线路法",{"key":23,"text":24,"correct":18},"D","定额计算法","关键线路法——是计划中工作与工作之间的逻辑关系肯定，且每项工作只估算一个 肯定的持续时间的网络计划技术。 计划评审技术——是计划中工作与工作之间的逻辑关系肯定，但每项工作的持续时间不肯 定，一般采用加权平均时间估算，并对按期完成项目的可能性做出评价的网络计划方法。 图示评审技术——是工作和工作之间的逻辑关系和工作的持续时间都具有不肯定性而按概 率处理的网络计划技术。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]