[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939075":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939075,606,2,"多选题","工程项目进度管理中，工作定义的成果包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作清单",true,{"key":16,"text":17,"correct":18},"B","项目范围说明书",false,{"key":20,"text":21,"correct":18},"C","项目网络图",{"key":23,"text":24,"correct":14},"D","工作分解结构的更新",{"key":26,"text":27,"correct":18},"E","工作顺序安排","AD","工作定义形成的文件包括：①工作清单和②工作分解结构的更新。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]