[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939073":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939073,606,2,"多选题","如果要减少项目进度计划的计算工期，可以采取的措施有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","增加人员",true,{"key":16,"text":17,"correct":18},"B","削减时差",false,{"key":20,"text":21,"correct":14},"C","赶工",{"key":23,"text":24,"correct":18},"D","增加平行作业",{"key":26,"text":27,"correct":14},"E","取消部分工作","ACE","进度计划的调整措施包括：(1)调整逻辑关系。(2)增、减工作的调整方法。(3)调 整资源的投入。(4)调整工作的持续时间。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]