[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939068":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939068,606,1,"单选题","工程网络计划中的费用优化，是指寻求( )的过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程总成本最低时的最短工期安排",true,{"key":16,"text":17,"correct":18},"B","工程直接成本最低时的工期安排",false,{"key":20,"text":21,"correct":18},"C","工程间接成本最低时的工期安排",{"key":23,"text":24,"correct":18},"D","给定费用下的最短工期安排","费用优化又叫工期成本优化，是寻求最低成本的最短工期安排，或按要求工期寻求 最低成本的计划安排过程。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]