[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939063":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939063,606,1,"单选题","工程项目进度管理中，可以称为软逻辑关系的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织关系",true,{"key":16,"text":17,"correct":18},"B","工艺关系",false,{"key":20,"text":21,"correct":18},"C","时间关系",{"key":23,"text":24,"correct":18},"D","工序关系","①工艺关系。生产性工作之间由工艺过程决定的，非生产性工作之间由工作程序决 定的先后顺序关系叫工艺关系。工艺关系也称为硬逻辑关系。 ②组织关系。工作之间由于组织安排需要或资源调配需要而规定的先后顺序关系叫组织关 系。组织关系也称为软逻辑关系，软逻辑关系可以由项目团队确定。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]