[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939060":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939060,606,2,"多选题","既保持项目范围不变，又能使关键线路长度减少的措施有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","增加资源",true,{"key":16,"text":17,"correct":18},"B","消除时差",false,{"key":20,"text":21,"correct":14},"C","赶工",{"key":23,"text":24,"correct":14},"D","调整逻辑关系",{"key":26,"text":27,"correct":18},"E","减少项目工作","ACD","本题考查的是项目进度控制方法。选项 E 属于项目范围变化。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]