[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939059":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939059,606,2,"多选题","下列进度控制过程的内容中，最先和最后进行的内容为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","出现进度偏差",true,{"key":16,"text":17,"correct":18},"B","分析偏差对其后续工作和总工期的影响",false,{"key":20,"text":21,"correct":18},"C","采取进度调整措施",{"key":23,"text":24,"correct":18},"D","采取相应的经济、组织、合同措施",{"key":26,"text":27,"correct":14},"E","进度监测系统","AE","本题考查的是项目进度控制方法。项目进度调整系统内容为：出现进度偏差→分析产生偏差的原因→分析偏差对后续工作和工期的影响→确定影响后续工作和工期的限制条件→采取进度调整措施→形成调整的进度计划→采取相应的经济、组织、合同措施→实施调整后的进度计划→ 进度监测系统。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]