[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939055":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939055,606,2,"多选题","工程项目实际进度与计划进度的比较方法主要有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","关键线路比较法",false,{"key":16,"text":17,"correct":18},"B","横道图比较法",true,{"key":20,"text":21,"correct":18},"C","S曲线比较法",{"key":23,"text":24,"correct":18},"D","前锋线比较法",{"key":26,"text":27,"correct":18},"E","列表比较法","BCDE","本题考查的是工程项目进度控制。将实际进度数据与计划进度数据进行比较，可以确定工程实际执行状况与计划目标之间的差距。常用的进度比较方法有：趋势分析、关键路径法和挣值管理。趋势分析包括：横道图比较法、前锋线比较法、S 形曲线比较法、香蕉曲线比较法、列表比较法。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]