[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939054":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939054,606,1,"单选题","工程项目进度管理中，计划评审技术对时间的估算采用（ ）估算方法。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总时间",false,{"key":16,"text":17,"correct":14},"B","最大可能时间",{"key":19,"text":20,"correct":14},"C","阶段时间",{"key":22,"text":23,"correct":24},"D","加权平均时间",true,"本题考查的是制定进度计划的依据。计划评审技术——是计划中工作与工作之间的逻辑关系肯定，但每项工作的持续时间不肯定，一般采用加权平均时间估算，并对按期完成项目的可能性做出评价的网络计划方法",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]