[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939052":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939052,606,1,"单选题","PERT 与 CPM 的根本区别在于 PERT 使用了（ ）时间估计。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最大可能",false,{"key":16,"text":17,"correct":14},"B","平均",{"key":19,"text":20,"correct":21},"C","加权平均",true,{"key":23,"text":24,"correct":14},"D","最小可能","本题考查的是制定进度计划的依据。PERT 与 CPM 的根本区别在于它使用了加权平均时间估算，做出来的进度安排计划要比 CPM 使用最大可能估算做出的现实。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]