[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939046":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939046,606,1,"单选题","某工作网络计划中，N 工作的最早开始时间和最早完成时间分别为第5 天和第8 天，最迟开始时间和最迟完成时间分别为第7 天和第10 天，则工作N 的总时差为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","3",{"key":22,"text":23,"correct":24},"D","2",true,"本题考查的是制定进度计划的方法。TFN＝LSN－ESN＝7－5＝2；或LFN－EFN＝10－8＝2。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]