[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939045":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939045,606,1,"单选题","某分部工程双代号时标网络计划如图9－16 所示，则工作B 的总时差和自由时差分别是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0天，0天",false,{"key":16,"text":17,"correct":18},"B","2天，0天",true,{"key":20,"text":21,"correct":14},"C","2天，2天",{"key":23,"text":24,"correct":14},"D","4天，0天","本题考查的是制定进度计划的方法。TFB＝min{0＋4、2＋0}＝2，FFB＝0。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]