[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939044":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939044,606,1,"单选题","某网络计划中，A 工作有两项紧后工作 B、 C，已知B 工作的最迟完成时间为24，持续时间为6 天；C 工作的最迟完成时间为28 天，持续时间为12 天，则A 工作的最迟完成时间是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","16天",true,{"key":16,"text":17,"correct":18},"B","18天",false,{"key":20,"text":21,"correct":18},"C","24天",{"key":23,"text":24,"correct":18},"D","28天","本题考查的是制定进度计划的方法。LFA＝min{LSB、LSC}＝min{24－6、28－12}＝16。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]