[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939042":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939042,606,1,"单选题","某双代号网络计划如下图所示，工作D 的总时差和自由时差分别为（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1天和1天",false,{"key":16,"text":17,"correct":14},"B","1天和2天",{"key":19,"text":20,"correct":14},"C","2天和1天",{"key":22,"text":23,"correct":24},"D","2天和2天",true,"本题考查的是制定进度计划的方法。ESD＝4，EFD＝6，LFD＝8，故TFD＝8－6＝2；ESF＝8，故FFD＝8－6＝2。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]