[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939041":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939041,606,1,"单选题","某工程单代号网络计划中，M 工作的最早开始时间和最迟开始时间分别是第 12 天和第 15 天，其持续时间为 6 天，M 工作有 3 项紧后工作，它们的最早开始时间分别是第 21 天，第 24 天，第 28 天，则 M 工作的自由时差是（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","3",true,{"key":20,"text":21,"correct":14},"C","4",{"key":23,"text":24,"correct":14},"D","8","本题考查的是制定进度计划的方法。 EFM＝12＋6＝18；FFM＝min{21－18、24－18、28－18}＝3。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]