[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939038":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939038,606,2,"多选题","选择缩短持续时间的关键工作进行工程项目工期优化时，应优先选择（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对质量影响不大的工作",true,{"key":16,"text":17,"correct":14},"B","增加费用最少的工作",{"key":19,"text":20,"correct":21},"C","持续时间最长的工作",false,{"key":23,"text":24,"correct":21},"D","可以最后进行的工作",{"key":26,"text":27,"correct":14},"E","有充足备用资源的工作","ABE","本题考查的是进度计划优化。选择应缩短持续时间的关键工作应考虑下列因素：（1）缩短持续时间对质量和安全影响不大的工作；（2）有充足备用资源的工作；（3）缩短持续时间增加费用最少的工作。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]