[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939030":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939030,606,1,"单选题","某工程拟将持续时间由15 天缩短为13 天，持续时间为15 天时总费用为10 万元，其中直接费用为8 万元，持续时间为13 天时直接费用为10 万元。缩短持续时间的间接费用率为0.1 万元\u002F天，则工程持续时间缩短后总费用为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","12.0万元",false,{"key":16,"text":17,"correct":14},"B","11.1万元",{"key":19,"text":20,"correct":21},"C","11.8万元",true,{"key":23,"text":24,"correct":14},"D","10.2万元","本题考查的是进度计划优化。 缩短持续时间工作的直接费用率＝（10－8）\u002F（15－13）＝1； 工期缩短后的总费用＝10＋（15－13）×（1－0.1）＝11.8（万元）",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]