[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939028":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939028,606,1,"单选题","在工程项目进度计划表示方法中，与横道图相比，时标网络图的优点是能够（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","明确表示各项资源需求量",false,{"key":16,"text":17,"correct":18},"B","明确表示各项工作之间的逻辑关系",true,{"key":20,"text":21,"correct":14},"C","直观表示各项工作的持续时间",{"key":23,"text":24,"correct":14},"D","直观表示工程进度计划的计算工期","本题考查的是进度计划编制的成果。时标网络图既表示项目的逻辑关系，又表示工作时间，而横道图对逻辑的表达不如时标网络图。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]