[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939026":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939026,606,2,"多选题","工程项目进度计划的表示方法包括（ ）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","横道图法",true,{"key":16,"text":17,"correct":14},"B","可交付成果法",{"key":19,"text":20,"correct":14},"C","进度曲线法",{"key":22,"text":23,"correct":24},"D","计划评审技术法",false,{"key":26,"text":27,"correct":24},"E","图示评审技术法","ABC","本题考查的是进度计划编制的成果。进度计划编制的成果：横道图法、时标网络图、里程碑法（亦称可交付成果法）、进度曲线法。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]