[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939023":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939023,606,1,"单选题","在工程项目建设中，普通人员及材料设备的需要量高峰值通常出现在（ ）阶段。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","前期",false,{"key":16,"text":17,"correct":14},"B","准备",{"key":19,"text":20,"correct":21},"C","实施",true,{"key":23,"text":24,"correct":14},"D","试生产及竣工验收","本题考查的是工作资源估算。工程项目实施阶段的主要任务是施工。施工是建筑物实体的生产，所需资源主要包括：劳动力、建筑材料和设备、周转材料、施工机械设备和临时设施以及后勤供应等。这些资源是工程项目实施必不可少的，它们的费用往往占工程总费用的80%以上。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]