[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939016":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939016,606,1,"单选题","关于双代号时标网络计划的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实箭线的水平投影长度表示该工作的持续时间",false,{"key":16,"text":17,"correct":14},"B","波形线表示工作与其紧后工作之间的时间间隔",{"key":19,"text":20,"correct":21},"C","时标网络计划宜按各项工作的最晚开始时间编制",true,{"key":23,"text":24,"correct":14},"D","双代号时标网络计划以水平时间坐标为尺度进行绘制","本题考查的是工作顺序安排。选项 C 错误，时标网络计划宜按各项工作的最早开始时间编制。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]