[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939006":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939006,606,2,"多选题","FIDIC 合同中，合同通用条件的条款中规定，可以给承包商合理延长合同工期的条件通常包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","延误发放图纸",true,{"key":16,"text":17,"correct":14},"B","延误移交施工现场",{"key":19,"text":20,"correct":14},"C","不可预见的外界条件",{"key":22,"text":23,"correct":24},"D","因施工作业所引起的污染",false,{"key":26,"text":27,"correct":24},"E","对公众所造成的损害","ABC","本题考查的是 1999 版 FIDIC 施工合同条件的主要内容。黑钻押题，金考典软件考前更新，下载链接 www.j inkaodian.com 通用条件的条款中规定可以给承包商合理延长合同工期的条件通常可能包括：延误发放图纸、延误移交施工现场、承包商依据工程师提供的错误数据导致放线错误、不可预见的外界条件、施工中遇到文物和古迹而对施工进度的干扰以及发生不可抗力事件等影响。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]