[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939005":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939005,606,2,"多选题","有关工程进度款支付，下列说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","付款周期应按照约定与计量周期保持一致",true,{"key":16,"text":17,"correct":18},"B","承包人应在每个付款周期开始向监理人提交进度付款申请单",false,{"key":20,"text":21,"correct":14},"C","监理人在收到承包人进度付款申请单后的 14 天内完成核查",{"key":23,"text":24,"correct":18},"D","监理人出具进度付款证书标明其已同意承包人完成的该部分工作",{"key":26,"text":27,"correct":14},"E","发包人应在监理人收到进度付款申请单后的 28 天内将进度应付款支付给承包人","ACE","本题考查的是施工合同履行。承包人应在每个付款周期末向监理人提交进度付款申请单，并附相应的支持性证明文件。监理人出具进度付款证书，不应视为监理人已同意、批准或接受了承包人完成的该部分工作。发包人应在监理人收到进度付款申请单后的 28 天内，将进度应付款支付给承包人。发包人不按期支付的，按合同的约定支付逾期付款违约金。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]