[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-938997":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},938997,606,1,"单选题","由于发包人提供的材料或工程设备不合格造成的工程不合格，需要承包人采取措施补救的，发包人应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承担由此增加的费用和（或）工期延误，并支付承包合理利润",true,{"key":16,"text":17,"correct":18},"B","承担由此增加的费用和（或）工期延误，不支付承包合理利润",false,{"key":20,"text":21,"correct":18},"C","承担由此增加的费用，工期延误和利润损失承包人承担",{"key":23,"text":24,"correct":18},"D","承担由此增加的费用和承包人利润损失，工期不予延误","本题考查的是施工合同履行。由于发包人提供的材料或工程设备不合格造成的工程不合格，需要承包人采取措施补救的，发包人应承担由此增加的费用和（或）工期延误，并支付承包合理利润。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]